Tanker Operations #03 - When to Go? |
| By President Mark Davis | |
| October 9, 2014 | |
When using traditional gravity tankers (tenders) in a shuttle operation, the sometimes "tricky" question is, "When do we to stop dumping water and go for another load." Ideally - each tanker should have a pre-determined "critical dump time" at which point the operator stops dumping. When using a 10-inch Newton-style dump, another reasonable rule of thumb is to stop dumping when the water drops below the 2-inch point on the chute - close the valve - and go get another load of water. Of course - this really depends on whether or not another tanker is in line waiting to get into position to dump. The worst decision is to wait until the water is just trickling out of the dump chute. Remember that a tanker shuttle is best served when units are moving in the shuttle and not waiting to offload every last drop of water. |
|